Pre-control is an alternative to control charting. A chart is prepared with the span between the specification limits (not the control limits) divided into colored bands:
Individual items are taken from the process, measured and plotted on the charts. The initial process adjustment, and subsequent patterns are based on the pattern of points:
Initial Adjustment (Qualification):
5 parts in a row are in the green |
OK to run |
1 part in the yellow |
restart the count |
two consecutive parts in the yellow |
|
one part in the red |
adjust the process and restart the count |
Operation:
take 2 consecutive parts from the process |
|
first part checked is green |
continue operation |
first part checked yellow |
check the second part |
second part green |
continue operation |
second part yellow or either part red |
stop and adjust the process |
|